Thane Borivali Tunnel Current Status Today: October 2026 Tracker

Quick Answer

Thane Borivali tunnel current status today (October 2026): tunnelling is under way from the Thane side with two boring machines, Nayak (launched 7 April 2026) and Arjuna (launched 13 August 2026). MMRDA reports 13.73% physical progress up to August 2026. On the Borivali side, launch-shaft excavation has started and the third machine is ready to ship. The official target is May 2028.

The Thane Borivali tunnel current status today is a question we hear at almost every site visit in Thane and Kandivali, and the answer has changed a lot in 2026. A year ago the project was mostly shafts, casting yards and paperwork. Now two of India’s largest tunnel boring machines are cutting rock under Sanjay Gandhi National Park, and MMRDA updated its official project page on 15 October 2026.

The project is an 11.84 km road link between Manpada on Ghodbunder Road in Thane and Magathane on the Western Express Highway in Borivali East. It is made up of 10.25 km of twin tunnels and 1.59 km of connecting roads. Once open, it is expected to cut a 60 to 90 minute peak-hour drive to about 15 to 20 minutes.

We at Godrej Properties MMR track every official update. This page is our main status tracker, refreshed whenever MMRDA publishes new figures. It covers where each side of the project stands, what has changed recently, and whether the schedule is holding.

Thane Borivali Tunnel Current Status Today: October 2026 Summary

Here is the official position, taken from MMRDA’s project page (last updated 15 October 2026) and the contract records.

Item Status today Source
Physical progress 13.73% (up to August 2026) MMRDA
Financial progress 13.13% (up to July 2026) MMRDA
TBM-01 “Nayak” Boring from Thane since 7 April 2026 MMRDA
TBM-02 “Arjuna” Boring from Thane since 13 August 2026 MMRDA
TBM-03 Factory test passed in Chennai on 29 May 2026; ready to ship to Borivali MMRDA
Borivali launch shaft Piling and excavation started; casting yard being set up MMRDA
Thane casting yard Tunnel lining segments being cast MMRDA
Approved cost Rs 16,600.40 crore MMRDA, March 2023
Target completion May 2028 (60-month contract) Contract; state review cited December 2028

Progress has picked up but is still early. Physical progress was 8.19% at the end of August 2025, so the project added about 5.5 percentage points in twelve months. Most of that year went on preparing shafts and assembling machines, which add little to the percentage but make faster progress possible later.

Thane Borivali Tunnel Status: What Changed in 2026

2026 is the year the project moved underground. These are the dated milestones that matter most, in order:

  • 26 February 2026: TBM Nayak passed its site acceptance test at the Thane launch shaft
  • 7 April 2026: Nayak was launched by the Chief Minister, and boring began from Thane
  • 29 May 2026: TBM-03 passed its factory acceptance test in Chennai, ready for the Borivali side
  • 25 June 2026: TBM Arjuna passed its site acceptance test
  • 13 August 2026: Arjuna was launched, so both Thane-side tubes are now being bored
  • 15 October 2026: MMRDA updated its project page, confirming tunnelling from Thane and shaft works at Borivali

Both machines have 13.34-metre cutter heads, which reports describe as the largest single-shield hard-rock TBMs used in India. They are cutting through the Deccan basalt under the national park. Hard rock is stable, which keeps the surface above undisturbed, but it is slow to cut and wears the cutters, so each machine stops regularly for maintenance. For a deeper look at the machines’ pace, see our progress-in-numbers analysis.

Thane Side vs Borivali Side: Where Each End Stands

The project is split into two contracts, both awarded to Megha Engineering and Infrastructures Ltd (MEIL) in May 2023. Package 2 is the Thane end (Rs 5,879 crore) and Package 1 is the Borivali end (Rs 6,178 crore). The two ends are moving at very different speeds, and that gap is the most important fact about the project’s status.

Work front Thane end (Package 2) Borivali end (Package 1) Why it matters
Portal location Tikuji-ni-Wadi, Manpada, Ghodbunder Road Magathane / Ekta Nagar, Western Express Highway Where traffic enters and leaves
Launch shaft Complete Piling and excavation in progress Machines cannot start without it
Casting yard Producing segments Being set up Supplies the tunnel lining
Boring machines 2 boring (Nayak, Arjuna) TBM-03 ready to ship; TBM-04 to follow Two-ended boring roughly halves the drive time
Land Available Clearance and rehabilitation took longer Main cause of the Borivali-side lag

Until the Borivali machines start, the tunnel is being dug from one end only. Each tube is about 10.25 km long, and the plan assumes the machines meet roughly halfway. Every month the Borivali launch slips adds pressure on the overall date. Our update on the Borivali shaft and TBM-03 covers that end in detail.

Is the Thane Borivali Tunnel on Schedule?

On the official record, the completion date is still May 2028, the end of the 60-month contract that began on 19 May 2023. In practice, few observers expect that date to hold for a full opening. A June 2025 state review already referred to December 2028. With about 19 contract months left and 86% of the work still to do, the project would need to average about 4% progress a month, many times its pace so far.

Our read: tunnel progress accelerates sharply once all four machines are boring, but the Borivali end has not started yet. We treat 2029 as the realistic opening year, with late 2028 as the best case.

A delay does not mean the project is in trouble. The hard parts, wildlife clearances, land at the Borivali end and launching the first machines, are mostly done. What remains is mostly execution. Our full analysis of the Thane Borivali tunnel completion date sets out the best, base and stress scenarios.

How to Check the Tunnel Status Yourself

You do not need to rely on a broker’s slide. These five checks, done once a quarter, tell you whether the project is speeding up:

  1. Read MMRDA’s project page. Look at the physical progress figure and its “till” month. Above 20% by mid-2027 would show real acceleration.
  2. Count the machines boring. The jump from two to four, with TBM-03 and TBM-04 launched at Borivali, is the biggest change still to come.
  3. Watch the Borivali shaft. News of TBM-03’s site acceptance test at Magathane is the trigger for two-ended boring.
  4. Compare physical and financial progress. They should move together. A widening gap can point to billing or contract issues.
  5. Note any official date change. A formal revision from May 2028 would reset market expectations along both portals.

What the Status Means for Homebuyers

The tunnel matters most to homes within a short drive of the two portals: Ghodbunder Road, Manpada and Kolshet in Thane, and Borivali East and Kandivali East in Mumbai. Prices in these pockets already include some of the tunnel premium. The practical rule is to match your possession date to a realistic opening date, not the May 2028 headline.

On the Mumbai side, Godrej Properties Limited’s Kandivali East projects sit a few kilometres from the Magathane portal. Godrej Reserve Kandivali East, with possession around 2030, lines up well with a 2029 opening. Ready homes nearby let you live there before the tunnel opens. Buyers weighing those options can read our Godrej Bliss Kandivali reviews. On the Thane side, the planned Godrej township on Ghodbunder Road is close to the Manpada portal.

Frequently Asked Questions

Q: What is the Thane Borivali tunnel current status today?

As of October 2026, two boring machines are tunnelling from the Thane side: Nayak since April 2026 and Arjuna since August 2026. Physical progress is 13.73% up to August 2026. At Borivali, launch-shaft excavation has begun and TBM-03 is ready to ship.

Q: How much of the Thane Borivali tunnel is complete?

MMRDA reports 13.73% physical progress up to August 2026 and 13.13% financial progress up to July 2026. That is up from 8.19% physical progress in August 2025.

Q: Has tunnelling started from the Borivali side?

Not yet. Piling and excavation have started at the Borivali launch shaft, and the casting yard is being set up. TBM-03 passed its factory test in Chennai on 29 May 2026 and is ready to be sent to Borivali.

Q: When will the Thane Borivali tunnel open?

The contract target is May 2028, and a 2025 state review referred to December 2028. Based on current progress, we expect an opening during 2029, with late 2028 as the best case.

Q: How long is the Thane Borivali tunnel?

The project is 11.84 km long: 10.25 km of twin tunnels under Sanjay Gandhi National Park and 1.59 km of connecting roads. It links Manpada in Thane with Magathane in Borivali East.

Q: Where can I see the official status?

MMRDA’s Thane-Borivali twin tunnel project page publishes the physical and financial progress figures and machine milestones. We update this tracker each time those figures change.

Conclusion

The Thane Borivali tunnel status in October 2026 is clear. The Thane end is boring with two machines, the Borivali end is building its shaft, and overall progress is 13.73%. The project is real and moving, but the May 2028 target looks optimistic. A 2029 opening is the sensible planning assumption.

If you are buying near either portal, our team can match possession dates to these timelines and arrange site visits in Thane and Kandivali East.

Leave a Comment

Find your perfect property

with expert guidance.

Mumbai, Maharashtra

Upcoming Godrej Project

Connect With Our Experts

Book your personal meeting with our real estate experts and find your perfect home.

© 2026 Godrej Properties MMR | All Rights Reserved.

Godrej Properties New Launch

Book Today!
Get Free Site Visit